The pour team requests a small final quantity. The dispatcher says a part load is available, and someone crosses the last full-size truck off the traffic schedule. Before changing the access plan, check what is actually smaller: the quantity ordered, the vehicle, or both.

Separate volume from vehicle size

Ask dispatch which vehicle will carry the balance and whether its approach, turning movement or receiving position differs from the earlier deliveries. Keep the concrete quantity on the order and the confirmed vehicle on the access schedule. Never infer the dimensions of a mixer from the amount on its ticket.

A late balance order

Imagine the last planned mixer leaves at 14:00. The team then requests a balance load that cannot arrive until 15:00. Even if the same truck returns with much less material, it is another visit with a new arrival and departure. Compare it with the available receiving slot and applicable work window. A verbal order for more concrete is not a release to occupy the road again.

Who confirms the last movement?

Record the balance order reference, vehicle, dispatch decision and contact who confirms space at the site. If the remaining time or access is unresolved, ask the supplier to hold dispatch at the agreed origin until the teams settle the booking.

Related guide: Traffic Diversion for Loading, Unloading & Concrete Casting Works Dubai. For authority information, see the Dubai RTA right-of-way utilisation service.

Discuss the final mixer access window.