A tower crane erection delivery programme can list arrival times without identifying which component is on which vehicle. A coordination manifest connects the component sequence to the vehicle movements used in the traffic proposal. It supports planning; it is not a lifting plan or an authority-issued transport document.
Use references the team can reconcile
Ask the erection supplier to provide component references and the intended delivery grouping. Link each delivery to the appropriate vehicle information and receiving point. Do not create technical component descriptions independently of the supplier. The manifest should help the erection, transport and traffic teams refer to the same load.
Recommended fields
Include delivery reference, supplier component reference, vehicle configuration, unloading position, sequence dependency, receiving contact and readiness status. Add the relevant layout revision and an update date. Keep proposed arrival times distinct from confirmed call-forward instructions so a draft programme does not trigger an unwanted movement.
Check dependencies
Identify which delivery can be received only after another component is unloaded or a shared space is released. Ask the erection team to confirm these dependencies. If a component arrives out of sequence, the traffic team needs a reviewed response rather than an assumption that the load can be placed somewhere else. Temporary storage can change the agreed road footprint.
Manage manifest revisions
Nominate one owner to issue updates and preserve the revision history. When a vehicle or load grouping changes, identify which layout or access assumption needs review. The permit coordinator should assess any resulting public-space change. A revised manifest does not amend an issued permit by itself.
Use the manifest in the readiness review
Compare the latest manifest with the available transport information, erection sequence and traffic drawings. Close mismatches before issuing operational instructions. Send HMJ the manifest alongside the site layout and existing permit documents to help scope traffic coordination. During delivery, use the agreed receiving and communication procedure rather than treating an estimated time in the manifest as automatic permission to enter.
Related permit guidance and project support
Read our ROWPS & RTA Road Closure for Tower Crane and Crane Erection Dubai. Consult RTA’s official right-of-way occupation service for the applicable Dubai requirements. The service scope depends on the location and proposed activity.
Request an HMJ project quotation or call +971 50 778 9046.
Account for accompanying vehicles
If the transport specialist specifies an accompanying vehicle, give it a separate movement entry linked to the trailer. Identify where the vehicles separate, who confirms access and when each leaves. Use the accompanying vehicle arrival and departure guide before finalising dispatch instructions.