A plan shows three rectangles beside a building. The facilities manager sees existing parking spaces; the contractor reads the same outlines as the area requested for works. Before a traffic drawing is issued for review, make existing features and proposed occupation distinguishable even on a monochrome copy.
Write a legend that answers two questions
Which lines identify features already on the street? Which lines identify the proposed work area for this stage? Ask the drawing team to use distinct labels or line styles and a clear stage reference, following the requirements for the project. Avoid relying on colour alone. Put a short label beside the proposed boundary wherever crossing lines could be misread.
Try the one-bay example
Suppose three bays appear in the survey but the supplier proposes to receive materials in only one. The drawing should let a reviewer identify that one bay and see whether the unloading movement extends beyond it. If the extent is still unknown, mark it for confirmation rather than using the entire row as a placeholder.
Check what the reader understood
Give the sheet to a colleague unfamiliar with the site. Ask them to point to the existing bays, the proposed occupied space and the part kept available. Compare their answer with the engineer’s intent. Clarify the legend or labels before recording the revised sheet in the application set.
Related guide: Traffic Management Plan Dubai. For authority information, see the Dubai RTA right-of-way utilisation service.