A supplier may offer a jib delivery as one transport load or as several sections. Before pricing traffic support, ask the crane specialist which configurations are technically acceptable. The traffic coordinator can then compare their effect on the street; the coordinator does not choose how the crane is assembled.

Compare movements, not just trailer count

For each acceptable option, list the actual trailers, approach streets, receiving order and destination of each load. Ask where components can be received inside the site. One long load may suit the internal programme but need a different access review. Multiple shorter loads may use the same gate more often, increasing the time it must remain available.

Example: the receiving space is shared

Three deliveries look straightforward on a drawing showing one short trailer. But if the first two sections remain in the only receiving space, the third truck has nowhere to unload. Ask the erection lead when space becomes available again and the haulier where the next vehicle stays before release. Record the dependency on the dispatch schedule.

Make the quote traceable

Put the selected configuration and supplier reference on the traffic quotation and drawing brief. If procurement later chooses the other package, reopen the street-access comparison and the applicable permit review before confirming deliveries.

Related guide: Traffic Diversion & RTA Permit for Tower Crane Erection Dubai. For authority information, see the Dubai RTA right-of-way utilisation service.

Discuss the traffic scope for your crane delivery.

Share This Story, Choose Your Platform!

Leave A Comment