A crane’s vehicle outline does not describe the complete space needed for its proposed setup. Specialist support or ground protection arrangements can extend the footprint and introduce additional delivery movements. For crane erection in Dubai, coordinate these confirmed inputs with the traffic layout before finalising road occupation boundaries.

Obtain the specialist layout

Ask the competent lifting and ground-assessment teams for the relevant support arrangement and its spatial requirements. Clearly distinguish preliminary information from a confirmed technical design. This article does not calculate bearing capacity, specify mat dimensions or assess underground structures. Those decisions require competent project-specific assessment.

Show the complete proposed footprint

Include the specialist support area alongside the crane, access route and public-facing work boundary. Identify interfaces with footpaths, parking, drainage features or other site constraints for the responsible teams to assess. A traffic drawing should not omit part of the setup merely because it is supplied by a separate contractor.

Plan delivery and placement

Confirm how support materials will arrive, where they will be unloaded and how the responsible contractor proposes to place them. Their delivery may need space before the crane reaches its final position. Record the sequence and identify any temporary occupation that is additional to the operating footprint. Technical handling methods remain with the competent contractor.

Review changes before mobilisation

If the specialist design changes the support footprint, compare it with the traffic arrangement and permit scope. Do not assume that the occupied area can be enlarged informally. The appointed coordinator should establish the required review or amendment process before the revised setup is implemented.

Include removal in the programme

The road may remain occupied after the crane departs if support materials still need collection. Record who arranges recovery, who checks the condition of the occupied area and how the handback is coordinated. Send HMJ the confirmed specialist layout, delivery and removal sequence, photographs and permit information. This gives traffic planners a complete basis for assessing the public-space interface.

Related guidance and project support

Read our Traffic Diversion & RTA Permit for Tower Crane Erection Dubai. For the applicable Dubai service requirements, consult RTA’s official right-of-way occupation service. Approval scope depends on the location and activity.

Request an HMJ project quotation or call +971 50 778 9046.

Which supplier removes the mats?

Identify the party releasing the supports for handling and the supplier collecting them. Record any gap between crane departure and pickup, and check it against the actual permitted occupation. Use the outrigger mat return booking checklist to close this part of the works.