RTA NOC Checklist Dubai – Everything You Need Before You Submit

Submitting an incomplete RTA NOC application is the fastest way to delay your Dubai road works project. The RTA rejects applications with missing documents immediately — no partial reviews, no provisional approvals. This checklist covers every item you need ready before hitting submit. HMJ Contracting prepares complete NOC submissions for clients across Dubai. Call +971 50 778 9046.

Pre-Submission Checklist

1. Traffic Management Drawings

Prepared to RTA standard — correct scale, dimensions, symbols, taper lengths calculated for road speed, TMA positioning, crash cushion placement, barrier locations, and signing distances. This is the document most likely to cause rejection if incorrect.

2. Traffic Management Plan

Written plan matching the drawings — working hours, phasing, pedestrian routing, emergency access, and diversion routes where applicable.

3. Equipment Schedule

Complete list: TMA specification and impact rating, crash cushion type and certification, number of barriers, signs, cones, and arrow boards.

4. Method Statement

Step-by-step description of how the works will be carried out, including setup, work activities, and clearance.

5. Project Programme

Start date, duration, working hours, and phasing schedule. Night works must be stated explicitly.

6. Reinstatement Plan

Required for any works disturbing road surfaces, footpaths, or kerbs. Shows how the area will be restored.

7. Contractor Credentials

Valid trade licence, contractor registration, and authorised signatory details.

8. Additional Documents (If Applicable)