Right of Way Permit Dubai RTA – How to Apply and What Is Required

The Right of Way (ROW) permit from RTA Dubai is the mandatory approval for any works within the public road reserve boundary. Understanding what is required, how to apply, and how to avoid common rejection reasons is essential for any contractor working near Dubai’s road network. HMJ Contracting manages ROW permit applications for clients across Dubai. Call +971 50 778 9046.

What Is the RTA Right of Way?

The Right of Way is the legally defined land corridor reserved by the RTA for roads, footpaths, utilities, and associated infrastructure. It extends beyond the carriageway edge to include verges, drainage channels, utility corridors, and in some cases landscaped areas. Any physical works within this boundary require a ROW permit — even if they do not touch the road surface itself.

Who Needs a Right of Way Permit in Dubai?

  • Utility companies installing or maintaining pipes and cables within road reserves
  • Developers connecting buildings to public utilities across the road reserve
  • Contractors installing or maintaining guardrails, signs, or street furniture
  • Infrastructure teams working on drainage or stormwater systems in road corridors
  • Construction companies installing site fencing adjacent to road reserves
  • Any party excavating within the road reserve boundary for any purpose

How to Get a Right of Way Permit from RTA Dubai

ROW permit applications are submitted through the RTA’s ROWPS portal (rowpermits.rta.ae). The application requires engineering drawings, a traffic management plan, a method statement, and a reinstatement plan — all prepared to RTA standard. HMJ prepares all required documents and manages the submission. See our full RTA Right of Way permit guide and ROW permits service page.

Right of Way Permit vs NOC – What Is the Difference?

Many projects require both. The ROW permit authorises physical access to and works within the road reserve. The NOC confirms the RTA has no objection to the proposed works. For most utility and infrastructure projects, both must be obtained before works start. HMJ manages both applications simultaneously to avoid delays. See our RTA NOC application guide.

Get Your Right of Way Permit

Call +971 50 778 9046. HMJ also provides all physical safety equipment for ROW works — TMA rental, crash cushions, and lane closure setup.