Repeated concrete pours can look identical on a construction programme while creating different traffic conditions at street level. A change in pump position, delivery volume or nearby access can alter the road occupation arrangement. For Dubai projects, build a date-by-date coordination schedule instead of assuming that approval for one pour automatically covers the next.

Create a pour and permit register

Use one row per planned pour. Record the date, proposed occupation window, location, pump layout reference, delivery assumptions and responsible coordinator. Add fields for the relevant permit reference, validity and unresolved comments. Keep the planning date separate from the approved work date so draft programme entries cannot be mistaken for permission to proceed.

Define what stays the same

Identify genuinely repeated elements: site entrance, pump position, mixer approach, pedestrian route and traffic-control layout. Refer to a controlled drawing revision rather than copying an old sketch into each briefing. Then record variables such as a second pump, a longer vehicle, different arrival direction or changes in neighbouring access. The project team should review these changes against the permit scope before each mobilisation.

Coordinate supply without promising road capacity

Ask the concrete supplier and site team to agree delivery sequencing using site-specific capacity. Do not treat the public approach road as spare mixer storage. Establish how dispatch will respond if the pour pauses or the gate is unavailable. A recurring programme benefits from consistent communication rules, but the traffic arrangement must still reflect the actual space and conditions on each date.

Review gaps and revisions

Check whether the planned dates and work stages fall within the applicable permit terms. If dates or scope change, verify the authority’s required renewal or amendment route through the responsible coordinator. Do not infer that a series of similar activities is covered by a single blanket permission. Keep superseded drawings clearly marked and ensure the site team receives the current authorised information.

Close one pour before releasing the next

After each operation, record access problems, equipment delays, surface condition and handback observations. Feed relevant changes into the next coordination review. For example, a recurring conflict with building deliveries should trigger a review of the sequence and public access arrangement, not an informal daily workaround. Send HMJ the complete proposed pour calendar, layout revisions and existing permit information to scope traffic diversion and ROWPS coordination support.

Related permit guidance and enquiries

Read our RTA Permit, ROWPS & Road Closure for Loading/Unloading & Concrete Casting Dubai. For the official service scope and application requirements, consult RTA: Apply for a Permit to Utilise Part of The Right-of-Way. Requirements vary with the proposed activity and location; the RTA guidance here concerns Dubai.

Request a project quotation from HMJ or call +971 50 778 9046.